Posted on

Slab inspection approved and poured

Griffith bsmt 2 Griffith Bsmt3 Griffith bsmt4 

Concrete is laid and looks great!  While taking a quick break, my Dad poses for a photo session… he is such a clown ;~)  The most hard working man I know!  Notice the pump truck’s boom… just long enough to get to the back of the house with the 32′ arm.  Thanks guy for a job well done!  And Thanks Bro for a company well run!

Posted on

Griffith job basement dig

We have completed the basement dig and will be getting the french drain installed around the perimeter.  The Superior Walls have been signed off on and have been released in to production.  Here are a few pics of the equipment doing the dig… job well done!

digging1  digging3  digging2  digging4

Posted on

Griffith Building Permit is posted on the job

Griffith bldg permit1  

The building permit has been approved and I have posted it on our “builder job site sign”.  We have been given the go ahead to start digging the basement footings for the Superior Wall System.  The weather is looking good for the next several weeks for the basement excavation and prep work.